Farney Lane - Espina to Main

Project Description

The reconstruction of Farney Lane from Espina Ave to Main Street. The project will include new pavement, curb and gutter, sidewalks, curb ramps, drive pads, street lighting, drainage, natural gas, sanitary sewer and water.

This Project's Map Location:

Pending

Planning /
Design

Construction

In Progress

Complete

Projected Start
11/18/2016
Projected End
6/23/2017
Actual Start
12/27/2016
Actual End
12/8/2017

Budget

$1,227,410

Expended

$1,603,517

Available

$0