3rd Street - Picacho Ave to Hadley Ave

Project Description

The reconstruction of Third Street from Picacho Ave to Hadley Ave. The project will include new pavement, curb and gutter, sidewalks, curb ramps, drive pads, street lighting, drainage, natural gas, sanitary sewer and water.

This Project's Map Location:

Pending

Planning /
Design

Construction

In Progress

Complete

Projected Start
8/20/2018
Projected End
2/25/2018
Actual Start
N/A
Actual End
N/A

Budget

$648,000

Expended

$0

Available

$648,000