Hadley Ave - Reymond St to Mesilla St

Project Description

The reconstruction of Hadley Ave from Reymond Street to Mesilla Street. The project will include new pavement, curb and gutter, sidewalks, curb ramps, drive pads, street lighting, drainage, natural gas, sanitary sewer and water.

This Project's Map Location:

Pending

Planning /
Design

Construction

In Progress

Complete

Projected Start
10/4/2017
Projected End
3/7/2018
Actual Start
10/4/2017
Actual End

Budget

$475,000

Expended

$126,175

Available

$348,825