6th Street - Parker to Palmer

Project Description

The reconstruction of Sixth Street from Parker to Palmer. The project will include new pavement, curb and gutter, sidewalks, curb ramps, drive pads, street lighting, drainage, natural gas, sanitary sewer and water.

This Project's Map Location:

Pending

Planning /
Design

Construction

In Progress

Complete

Projected Start
11/2/2015
Projected End
6/22/2016
Actual Start
11/3/2015
Actual End
8/3/2016

Budget

$261,200

Expended

$176,725

Available

$84,475