Capital Improvement Project
CIP for Breland Hall - ID No: 184.2.1
Building No.
184
Facility
Breland Hall [
Floor Plans
]
Room/Space
Exterior Accessible Route
Space Type
Exterior Accessible Route
Urgency
High
Priority Level
Priority-One
Difficulty
Difficulty Level 2: More Difficult to Achieve
CIP Tracking
In House M&O
Survey No
1.20
Related ADA Code Lookups:
[
403.3
]
Project No.
2
Project Name
Exterior Accessible Route Improvements
Project Description
The ramp walkway closest to the southwest entrance is damaged and too steep to be compliant. Correct the slope on the concrete ramp at the southwest entrance to bring into compliance.
No.
Description
Cost:
Quantity
Unit
CIP Code
Severity
MACC
TPC
Remove concrete, correct slope and install new concrete
$3470.00
$4424.25