CIP for Chemistry Building - ID No: 187.9.1
Building No.
187
Facility
Chemistry Building [
Floor Plans
]
Room/Space
101 Interior Door
Space Type
Interior Doors
Urgency
Low
Priority Level
Priority-Two
Difficulty
Difficulty Level 2: More Difficult to Achieve
CIP Tracking
In House M&O
Survey No
2.44
Project No.
9
Project Name
Interior Door Modifications
Project Description
Approach space is lacking on the pull side of the door for maneuvering clearance. Renovate to provide the approach space on the pull side of the door and bring into compliance.
No.
Description
Cost:
Quantity
Unit
CIP Code
Severity
MACC
TPC
Move door to flush with hallway
$1165.48
$1561.74