Architectural Research Consultants, Incorporated
Return CIP List
Return Facility Menu
Return Main Menu
Capital Improvement Project
CIP for Speech Building - ID No: 365.56.1
Building No.
365
Facility
Speech Building [
Floor Plans
]
Room/Space
Interior Doors 2nd Floor - clearance
Space Type
Interior Doors
Urgency
Medium
Priority Level
Priority-Two
Difficulty
Difficulty Level 2: More Difficult to Achieve
CIP Tracking
In House M&O
Survey No
2.44
Project No.
56
Project Name
Interior Door Modifications
Project Description
The clearance at push and/or pull side at the door is non-compliant in rooms 237, 234F, 245A,D, ST1. Move the existing doors to provide clearance to comply with ADA requirements.
No.
Description
Cost:
Quantity
Unit
CIP Code
Severity
MACC
TPC
Move existing doors
$5827.40
$7808.72