Architectural Research Consultants, Incorporated
Return CIP List
Return Facility Menu
Return Main Menu
Capital Improvement Project
CIP for Computer Center - ID No: 126.12.1
Building No.
126
Facility
Computer Center [
Floor Plans
]
Room/Space
Door Hardware
Space Type
Urgency
High
Priority Level
Priority-Two
Difficulty
Difficulty Level 1: Readily Achievable
CIP Tracking
RFP
Survey No
2.46
Related ADA Code Lookups:
[
404.2.7
]
Project No.
12
Project Name
Interior Door Modifications
Project Description
Many doors on the first floor and most doors on the second floor have knob hardware. Replace the door hardware with ADA compliant lever-type handsets.
No.
Description
Cost:
Quantity
Unit
CIP Code
Severity
MACC
TPC
Replace interior door hardware
$89400.00
$119796.00